Levanen Underground
Teamwork builds....
Our ongoing projects across Minnesota reflect the depth and scope of our capabilities. Each opportunity showcases our dedication to serving you, our valued customer, with excellence. Whether it’s summer or winter, we remain steadfast in our commitment to supporting our local communities, delivering quality work no matter the season.

Water Treatment Plant & Well Improvments
We were honored to be awarded the contract for the City of Atwater’s Water Treatment Plant and Well Improvement Project. This facility represents our continued commitment to safe, modern infrastructure and clean water systems for Minnesota communities. Levanen Underground is proud to take part in essential public works like these—and we look forward to taking on more projects like this in the years ahead.
2025 Lead Water Service Line Replacement
This spring, we were proud to once again support our local municipal communities across Minnesota by taking on another vital public infrastructure project. This effort involves the replacement of 42 residential water service lines—part of an initiative to eliminate aging lead piping installed decades ago. Levanen Underground is committed to helping deliver clean, safe drinking water to the families and homes we serve. Photo or Video Coming soon.


Civic Center Ice Arena
Litchfield, MN
In March 2025, we began the removal and replacement of our local ice rink—one that many of us at Levanen Underground proudly skate on every week. With the anticipation of a brand-new addition to the facility and the challenge of tight grading tolerances, precise piping, and coordinated execution, our team eagerly took it on. We're excited to see our community back on the ice in Fall 2025, enjoying a space built with pride, precision, and local passion.
Motor Condos
Independence, MN
Above and beyond—this project stands as one of the most exciting and challenges we have for 2025. With over 20,000 feet of combined sewer, water, and storm infrastructure to be installed across multiple phases, Levanen Underground is proud to lead the charge in upgrading essential services for this growing community.
This multi-stage development will span two to three years, allowing for efficient utility phasing and coordination across phases 1A, 1B, 1C, 2A, and 2B. With detailed planning and our crews fully aligned, the work fits perfectly within our schedule. We're excited to see this project deliver long-lasting benefits to local residents and businesses.


Water System Improvements
Webster, SD
We are excited to share that we have successfully completed Phase Two of the Webster Water project in Webster, SD! This phase included 60 water services and a few thousand feet of 6" main line The project went very well, and we are proud of the results.
City of Willmar
10th Street NW Improvement Project
In 2024 we were proud to complete a significant municipal project in Willmar MN. This involved reconstruction of two blocks of sewer, water, and storm systems, along with the replacement of sidewalks and curb and gutter.


National St Water Service Project
Blaine, MN
In January 2024, we successfully completed a challenging winter project in Blaine, boring 512 feet of 1" water service lines to two homes. This project highlighted our commitment to quality and expertise, ensuring reliable water supply for our clients. We look forward to taking on more rewarding projects in the future!